the builder and the architect . . . |
|
. . . we are verifying the wall heights . . . |
|
. . . and things are working out well! |
It is with the greatest pleasure that Ican tell you, we arein Phase2 and that means in approx. 2 months the entire project could be finished.
Todays site meeting was to confirm the heightof the new buildings and therefor the roofs and we also had Jones there to verify the details and the materials. Vernon and his team under the ledership of Maurice is working very hard and very well, we found a 4 millimeter discrepancy on one wall, wow, I must say, that is very little!!!
Niels and Susi, now regular visitors from Durban, enjoyd the new views andI guess, we all are looking forward to the end. Anniki and Nora are also more than positive and it is really great to be in a project that generates this kind of enthusiasm!!!
And let it be done, well, I will be on site like once a weekand report as much as I can . . .
yours
Dustin
|
Niels and Susi on their phone |
|
|
Vernon and Jones (Durban vs. Soweto) |
|
|
Lucky, our electritian ( . . . Orlando . . . ) |
|
Maurice, the one in charge |
|
|
chatting under the shade |
|
|
Lucky inspecting the holes for the transformers |
|
|
the northern edge |
|
|
a view from the 'library' |
|
|
working on the hall |
|
|
more materials to be used |
|
|
this looks like the future lecture room |
|
|
wow! sinks installed |
|
|
and instalation complete. |
|
|
an idea of the final structure |
|
the old kitchen will soon go |
|
Grade-10 girls on project! |