Today, Thursday the 10th of February 2011 marked the start of our
Construction work with the new contractor (Magane Enterprises). As we
all know that we met with them last Thursday to agree on the work and
to be done and all the terms of reference, they have now started the
work after receiving the Contract of work with the Job Description,
Specifications and the expectations.
Today (Thursday 10 February 2011) in the morning they started by
digging the foundation in the Main Hall so as to add the third line of
bricks on the Foundation. That was successfully done and finished.
After digging the foundation we the moved to preparing and pouring
concrete on the foundation for the Library. We managed to reach halfway
and are going to finish tomorrow before lunch. The new team together with
the Volunteers were all in high spirits and that made it all possible to achieve
what we achieved today.
concrete on the foundation for the Library. We managed to reach halfway
and are going to finish tomorrow before lunch. The new team together with
the Volunteers were all in high spirits and that made it all possible to achieve
what we achieved today.
The plan for Friday the 11th of February is to finish pouring the
concrete for the library and possibly start brick-laying on the
foundation for the main Community Hall.
by Webster Magunje (Humana)